Cedar Falls Water Reclamation Facility

The Cedar Falls Water Reclamation project includes a new $10.2M GPD final clarifier, bio-solids building with two BDP felt filter presses, new ultraviolet disinfection building with ozonia UV system, sludge thickening and system automation controls. The project included installing new systems while taking existing systems off-line, yet maintaining DNR-allowed output into the Cedar River. Dewatering systems were required during excavation to prevent water infiltration from the Cedar River.


© Copyright 2022 Woodruff Construction, Inc. All Rights Reserved.