Fairfield Lift Station
The lower level of the project consisted of construction of a cast in place concrete sanitary sewer lift station, including the submersible pumps, automatic bar screen, mechanical washer compactor and process piping.
The upper level of the project consisted of the construction of precast concrete lift station 3,400 SF building and associated electrical and mechanical equipment and components.
Additional site improvements consisted of 340 LF of 36” diameter sanitary sewer, 125 LF of 24” diameter of sanitary sewer and about 120 LF of 14” diameter of sanitary sewer.