Hubbard Swimming Pool
This project consisted of the complete demolition of an existing pool facility and the construction of new. The project began August 2022 and was completed in June of 2023. The biggest challenge of the project was the cast in place concrete pool which Woodruff self-performed. In order to meet schedule and due to other multiple circumstances, the pool was built during winter (started October 2022 and completed in February 2023). But with good planning, the right team and some hard work, the pool was successfully completed per the schedule. The small town of Hubbard and their many “sidewalk inspectors” were very impressed with our progress throughout the entire project and very happy with the end results.